LocationSan Jose, CA
Owner

County of Santa Clara, Valley

Health and Hospital System

Completion Date2009
Project TypeNew Construction


Valley Specialty Center

Lawrence Livermore National Laboratory, Data Center Building 112 Renovation

Selected Projects

LocationBerkeley, CA
Owner

U.S. Department of Energy

Completion Date2014
Project TypeNew Construction


Lawrence Berkeley National Laboratory

Computation Research / Training Facility (CTRF)

Sherrill Engineering provided retro-commissioning services for the Pacific Energy Center, a 30,000-square-foot multipurpose office building and public information center. The building is a showcase for energy efficiency programs.  Sherrill Engineering commissioned the VAV and multizone HVAC, chiller/ice storage, heating hot water, lighting, day lighting and control systems. Following the commissioning project, energy consumption was reduced by 25% for two years and remains below previous levels.

PG&E Pacific Energy Center

LocationSan Francisco, CA
Owner

Pacific Gas & Electric Company

Completion Date2001
Project TypeRetro Commissioning


Sherrill Engineering provided commissioning services for the addition of nine 20,000 cfm computer room air handling (CRAH) units in building 112, a 70,000-square-foot data center facility undergoing phased renovation while operating at partial capacity. Sherrill Engineering identified several opportunities for operational, reliability and energy efficiency improvements.  We facilitated completion of those that were low- or no- cost, while providing analysis and guidance for addressing those opportunities requiring further coordination and/or investment.

Consulting Mechanical Engineers

Sherrill Engineering provided comprehensive HVAC and Electrical System commissioning design review and control system coordination services for the new “CRTF” High Performance Computing (HPC) facility being built at the Berkeley Lab campus.  This facility is slated to house the National Energy Research Scientific Computing Center (NERSC) and the world’s fastest “supercomputer” capability upon completion.  Systems commissioned include, Chilled Water, Air Handling, underfloor air distribution, reheat, Exhaust and Economizer systems, Air Terminals, HVAC Controls, Lighting Controls, Normal and Emergency Power Service and Distribution, and backup generator systems.

Sherrill Engineering provided detailed design and construction phase commissioning services to the County of Santa Clara for the new Valley Specialty Center, a 6-floor, 250,000 sq. ft. outpatient facility comprising a variety of procedure, examination, office, conference and pharmacy spaces. Systems commissioned include Complete HVAC and Controls, Plumbing, Electrical including normal and emergency power distribution and lighting controls, Elevators and Pneumatic Tube systems.

LocationLivermore, CA
OwnerU.S. Department of Energy
Completion Date2010
Project TypeRenovation Commissioning


Sherrill Engineering, Inc.